FIGUEIRA DA FOZ BRIDGE

FIGUEIRA DA FOZ BRIDGE
Figueira da Foz, Portugal

Project Description

Cable stayed Bridge over the Mondego River with steel deck , a central span with 225m, and
pre-stressed concrete access viaducts with a continuous an curve structure. The concrete
towers of the bridge rise 85m over the water level.
Cable stayed Bridge over the Mondego River with steel deck , a central span with 225m, and pre-stressed concrete access viaducts with a continuous an curve structure. The concrete towers of the bridge rise 85m over the water level.

Implemented services

Concept, Preliminary and Detailed Designs of structures, including
Site Technical Assistance during Construction and Load Tests.
Concept, Preliminary and Detailed Designs of structures, including Site Technical Assistance during Construction and Load Tests.

Year
1983

Client Name
Ministério das Obras Públicas, JAE